RFI Process¶
Purpose¶
Raise a formal question and track it through to a recorded response and closure.
Role required¶
Super Admin or Admin.
Steps¶
- Create the RFI — subject, question, priority, raised date, and response-required-by date.
- Wait for or chase a response ahead of the due date, using the Calendar to track it.
- Record the response.
- Close the RFI once resolved.
Expected result¶
The RFI moves Open → Responded → Closed, with the response text recorded against it.
Linked modules¶
Common mistakes¶
- Letting an RFI sit past its response-required-by date without following up — check the Calendar's Overdue filter regularly.
What to do next¶
Check whether the RFI's answer affects the Programme or requires a Variation.