Site Report Process¶
Purpose¶
Record a daily site diary entry.
Role required¶
Super Admin or Admin.
Steps¶
- Create the site report — date, weather, workers on site, works carried out, materials delivered, issues and delays.
- Set the status to Submitted once complete, and Approved once reviewed.
- Edit the entry later if a correction is needed.
Expected result¶
A dated record of site activity that forms part of the project's evidence trail (useful for delay events, variations, and disputes).
Linked modules¶
- Site Reports
- Delay and EOT — site reports are useful evidence for delay events
Common mistakes¶
- Leaving gaps in the site diary — a continuous record is far more useful as evidence than sporadic entries.
What to do next¶
Reference relevant site report dates when raising a delay event or responding to an RFI.